- Download the Lab Audit Profile Form: Download Lab Audit Application
- Download a free copy of HI 40.7 - HI Pump Test Laboratory Approval Program Guide: Download HI 40.7
- Purchase a copy of HI 40.6: Methods for Rotodynamic Efficiency Testing, become familiar with its requirements to determine if your testing facility is in compliance prior to scheduling an audit: Purchase HI 40.6
- Review your pump test laboratory procedure in comparison to the audit requirements of HI 40.7 to ensure that your facility is fully compliant and prepared for an audit.
- Complete the Lab Audit Profile form (one form per lab to be audited) and return to PTLAP@Pumps.org.
- Upon receipt of the Lab Audit Profile form, HI will send a price quote along with a Service Agreement requiring approval and signature.
- Once HI receives the signed Service Agreement and payment (per audited lab) your application package will be considered complete.
- Within thirty (30) days of receipt of the Service Agreement and payment, HI will forward the completed application to the third-party auditor for review.
- Within thirty (30) days of receipt of the completed Application, the auditor will contact you to schedule the audit.
- Based on the availability and proximity of auditors, on site audit scheduling time frame will vary, but every effort will be made to finalize these arrangements in a timely manner.
For administrative questions about the program and audits, contact PTLAP@Pumps.org (in writing for purposes of clarity). For technical questions about HI 40.6 or HI 40.7 please contact HI’s Technical Director Peter Gaydon
|